If a production gets behind schedule, one can add more 

programmers and catch up.

(A) True

(B)False

1 Answer

Answer :

(B)False

Related questions

Description : Which one of the following is not a software myth? (A) Once we write the program and get it to work, our job is done. (B) Project requirements continually change, but ... not understand how to control software projects internally, it will invariably struggle when it outsources software projects.

Last Answer : (D) If an organization does not understand how to control software projects internally, it will invariably struggle when it outsources software projects.

Description : To crash a schedule you should: 1. Increase the time allowed on those tasks that have float.  2. Try to increase expenditures of time only those tasks that are behind schedule.  3. Replace those ... to par with the busy.  4. Increase work efforts on those tasks that are on the critical path.

Last Answer : 4. Increase work efforts on those tasks that are on the critical path.

Description : When calculating EVM, Peter noticed that the cumulative planned value is 150%  of the cumulative earned value. What does this mean? Select one: a. SPI1, so the project is OK to complete on time. c. SPI1, so the project is behind schedule. e. SPI>1, so the project is on schedule.

Last Answer : a. SPI

Description : The project manager works with the project sponsor to identify the necessary resources  and team members needed to further develop the key project parameters – Cost, Scope,  Schedule, and Quality (CSSQ). (True/False)

Last Answer : Ans. True

Description : Scope, cost, and schedule are some of the parameters used for project negotiation.  (True/False)

Last Answer : Ans. True

Description : Jim Smith, the project manager for a high-profile project, has permitted the users to  add additional features to the systems project. The schedule and costs are now running  over. This project suffers from poor standards.

Last Answer : Ans: False

Description : A functional lead manages a group of programmers and technical staff members

Last Answer : Ans: False

Description : Five dimensions that must be managed on a project (A) Constraint, Quality, Cost, Schedule, Staff (B) Features, Quality, Cost, Schedule, Staff (C) Features, priority, Cost, Schedule, Staff (D) Features, Quality, Cost, Schedule, customer

Last Answer : (B) Features, Quality, Cost, Schedule, Staff

Description : . An important aim of a post-project review is to: a. validate overall progress to date against the budget and schedule. b. capture learning and document it for future usage. c. ... of all permanent documentation, signed by the sponsor. d. establish that project benefits have been identified.

Last Answer : b. capture learning and document it for future usage.

Description : The document that identifies what information needs to be shared, to whom, why, when and how is called the: a. communication management plan. b. stakeholder mapping grid. c. document distribution schedule. d. responsibility assignment matrix.

Last Answer : a. communication management plan.

Description : Which one of the following is not considered in resource management? a. Identifying resources. b. Influencing resources. c. Assigning resources to activities. d. Matching resources to the schedule.

Last Answer : b. Influencing resources.

Description : Which one of the following is a valid project Key Performance Indicator (KPI)? a. Staff appraisals. b. Management buy in. c. Milestone achievement. d. Master schedule.

Last Answer : c. Milestone achievement.

Description : . A schedule activity may begin 10 days before the predecessor activity finishes. This is an example of: A. Finish-to-Start B. Start-to-Finish C. Start-to-Start D. Finish-to-Finish

Last Answer : A. Finish-to-Start

Description : . If the Earned Value is equal to Actual Cost, it means: A. Project is on budget and on schedule B. Schedule Variance Index is 1 C. There is no schedule variance D. There is no cost variance

Last Answer : D. There is no cost variance

Description : A Project with a total funding of $100,000 finished with a BAC value of $95,000. What term can BEST describe the difference of $5,000? A. Cost Variance B. Management Overhead C. Management Contingency Reserve D. Schedule Variance

Last Answer : C. Management Contingency Reserve

Description : In the project planning, which of the following is considered as the most basic parameter  based on which all other estimates are made? A. project size B. project effort C. project duration D. project schedule

Last Answer : A. project size

Description : Complete the following statement. The method of incorporating change into  project planning and execution processes is called the: Select one: a. project logic diagram. b. change management process. c. milestone schedule d. critical path e. rough order of magnitude

Last Answer : b. change management process.

Description : Which of the following project baselines provides the basis for measurement of  the expected cash flow against requirements over time and is often displayed as an  S curve? Select one: a. Schedule baseline b. Cost performance baseline c. Scope baseline d. Plan baseline e. Initiation baseline

Last Answer : b. Cost performance baseline

Description : Which of the following is typically a written document that defines what work  will be accomplished by the end of the project? Select one: a. Scope of work (SOW) b. Project logic diagram c. Milestone schedule d. Ballpark estimate e. Work breakdown structure

Last Answer : a. Scope of work (SOW)

Description :  A project budget estimate that is developed with the least amount of  knowledge is known as which of the following? Select one: a. Rough order of magnitude (ROM) estimate b. Scope of work estimate c. Conceptual estimate d. Line estimate e. Milestone schedule estimate

Last Answer : c. Conceptual estimate

Description : Subsequent to preparing ____, the team plans the project schedule and budget

Last Answer : Ans. Work Breakdown Structure

Description : dimensions that must be managed on a project (A)Constraint, Quality, Cost, Schedule, Staff (B)Features, Quality, Cost, Schedule, Staff (C)Features, priority, Cost, Schedule, Staff (D)Features, Quality, Cost, Schedule, customer

Last Answer : (B)Features, Quality, Cost, Schedule, Staff

Description : Amount of work completed to date compared with planned in the Earned Value  Management method is  A. Schedule Performance Index  B. Cost Performance Index  C. Percentage Complete  D .Percentage Spent

Last Answer : C. Percentage Complete

Description : A schedule performance index (SPI) of 0.76 means:  A. You are over budget B. You are ahead of schedule  C. You are only progressing at 76 percent of the rate originally planned  D. You are only progressing at 24 percent of the rate originally planned

Last Answer : C. You are only progressing at 76 percent of the rate originally planned

Description : The most common reason for schedule and cost overruns that surface after the project  is underway is scope creep.

Last Answer : Ans: True

Description :  The project team has just determined that the deadline for completion will not be met.  In order to deliver a high quality system on schedule, the team has requested that the  features be ... that a fixed deadline be imposed for the project. This technique  is referred to as SDLC methodology.

Last Answer : Ans: False

Description : Scope creep is only a minor factor in projects running over schedule, and every effort  should be made to incorporate any changes into the present system if they would truly be  beneficial.

Last Answer : Ans: False

Description : Estimates from the planning stage will need to be refined as the project progresses,  because it is virtually impossible to develop an exact assessment of the project’s schedule  before the analysis and design phases are conducted.

Last Answer : Ans: True

Description : The _____ is a dynamic schedule that logs and monitors all of the tasks that need to be  accomplished for the length of the project.  a. margin of error  b. project manager  c. project objective d. timebox  e. work plan

Last Answer : e. work plan

Description : The most significant challenge to project managers is _____.  a. lack of project management training  b. no one really understands how to manage a complex systems development project  ... tools that can assist in controlling project progress  d. unrealistic schedule demands by project sponsors

Last Answer : d. unrealistic schedule demands by project sponsors

Description : What is the definition of Earned Value Management? A. An approach that combines the scope, schedule, and cost baseline into a project  performance and progress measurement tool.  B. ... approach that combines the scope and cost baseline into a project performance and  progress measurement tool.

Last Answer : A. An approach that combines the scope, schedule, and cost baseline into a project  performance and progress measurement tool.

Description : Earned value management integrates scope, cost, and schedule measures to:  A. assess project performance and progress.  B. develop a preliminary budget. C. assess communication effectiveness among project team members. D. assess whether all requirements were met.

Last Answer : A. assess project performance and progress.

Description : You are the project manager working on a research project for a new drug treatment. Your preliminary project schedule runs past the due date for a federal grant application. The manager of the R&D ... .  A. Crashing B. fast tracking C. resource leveling D. adjusting the resource calendar

Last Answer : A. Crashing

Description : The project schedule is used to determine all of the following except which one?  A. Cost estimates B. Activity start dates C. Float times D. Activity end dates

Last Answer : A. Cost estimates

Description :  In a project schedule, the sequence of activities which cannot be delayed during the  course of the project without extending the project end date is referred to as the:  A. Action plan B. Critical path C. Schedule baseline D. Slack line

Last Answer : B. Critical path

Description : Which of the following is displayed as an S curve?  A. Gantt B. Cost baseline C. Critical path D. Schedule baseline

Last Answer : B. Cost baseline

Description : The network diagram is the best tool for demonstrating:  A. Schedule variances B. Resource requirements C. The sequence of project activities  D. Schedule performance over time

Last Answer : C. The sequence of project activities

Description : What are the key components in the "Triple constraint Triangle"?  A. Scope, Schedule, Cost, Project Manager B. Scope, Time, Cost, Project (Ans.) C. Time, Money, Scope, Project D. Project Manager, Time, Scope, Money

Last Answer : B. Scope, Time, Cost, Project (Ans.)

Description : A schedule activity may begin 10 days before the predecessor activity finishes. This is an  example of: A. Finish-to-Start B. Start-to-Finish C. Start-to-Start D. Finish-to-Finish

Last Answer : A. Finish-to-Start

Description : . If the Earned Value is equal to Actual Cost, it means: A. Project is on budget and on schedule B. Schedule Variance Index is 1 C. There is no schedule variance D. There is no cost variance

Last Answer : D. There is no cost variance

Description : A Project with a total funding of $100,000 finished with a BAC value of $95,000. What term  can BEST describe the difference of $5,000? A. Cost Variance B. Management Overhead C. Management Contingency Reserve D. Schedule Variance

Last Answer : C. Management Contingency Reserve

Description : An important aim of a post-project review is to:  a. validate overall progress to date against the budget and schedule.  b. capture learning and document it for future usage.  c. ... of all permanent documentation, signed by the sponsor.  d. establish that project benefits have been identified

Last Answer : b. capture learning and document it for future usage.

Description : The document that identifies what information needs to be shared, to whom, why, when and  how is called the: a. communication management plan.  b. stakeholder mapping grid.  c. document distribution schedule.  d. responsibility assignment matrix.

Last Answer : a. communication management plan.

Description : Which one of the following is not considered in resource management?  a. Identifying resources.  b. Influencing resources.  c. Assigning resources to activities.  d. Matching resources to the schedule.

Last Answer : b. Influencing resources.

Description : A Project control system: 1. Monitors and controls the project's schedule, costs, scope, budgets etc  2. Is a mechanism which reacts to the current project status in order to endure ... 4. Is a system for controlling and executing project documentation in an uniform and timely  manner

Last Answer : 1. Monitors and controls the project's schedule, costs, scope, budgets etc

Description : The Scope Baseline is: 1. the original description of the project's end results  2. a summary description of the project's original content and end product, including basic  budgetary and time constraint data 3. the original project budget and schedule  4. a and c

Last Answer : 2. a summary description of the project's original content and end product, including basic  budgetary and time constraint data

Description : The Scope Statement should contain which of the following? 1. Project schedule  2. Project budget constraints  3. Summary of project tasks , deliverables and resources required  4. Project objectives

Last Answer : 4. Project objectives