Curve inspection shall be carried out by Sectional PWI
a. Once in three months
b. Once in six months
c. Once in four months*
d. None of above

1 Answer

Answer :

c. Once in four months

Related questions

Description : Special inspection of distressed bridges Group II shall be carried out by Inspector (Concerned) is a) Once in three months* b) Once in two months c) Once in a month d) Once in six months

Last Answer : a) Once in three months*

Description : Special inspection of distressed bridges shall be carried out by Asst. Engineer is a) Once in three months b) Once in two months* c) Once in a month d) Once in six months

Last Answer : b) Once in two months*

Description : Sensitivity calibration against temp. variation shall be carried out. (i) At least once in month* (ii) quarterly. (iii) at least once in six months (iv) Any of above.

Last Answer : i) At least once in month*

Description : Lowest level of staff/supervisor competent for Organising Hot weather patrolling during summer months in LWR/CWR. a. Gangmate b. PWI* c. Keyman d. PWS

Last Answer : b. PWI*

Description : riodicity of recording of camber in PSC girders a) Once in a year* b) Once in two years c) Once in three years d) During the detailed inspection of SE/Br.

Last Answer : a) Once in a year*

Description : Lowest level of staff/supervisor competent for passing of first train after buckling in LWR/CWR. a. PWI* b. PWS c. Gangmate d. Keyman

Last Answer : a. PWI*

Description : Lowest level of staff/supervisor competent for all operations regarding distressing in LWR/CWR. a. PWI* b. PWS c. Gangmate d. Keyman

Last Answer : a. PWI*

Description : Lowest level of staff/supervisor competent for packing or renewal of single isolated sleeper not requiring lifting or slewing of track in LWR/CWR. a. PWI b. Keyman c. Gangmate* d. PWS

Last Answer : c. Gangmate*

Description : Lowest level of staff/supervisor competent for Lifting/Lowering of track in LWR/CWR. a. Keyman. b. Gangmate. c. PWI. d. PWS.*

Last Answer : d. PWS.*

Description : Lowest level of staff/supervisor competent for TTM tamping operation in LWR/CWR. a. Gang Mate b. PWS c. PWI* d. Keyman.

Last Answer : c. PWI*

Description : Periodicity of Under water inspection a) Once in a year b) Once in two years* c) Whenever high flood occurs d) Along with detailed inspection of SE/Br

Last Answer : b) Once in two years*

Description : Periodical inspection of PSC & Composite girders a) Once in 3 years b) Once in 5 years * c) Once in 2 years d) Once in 5 years

Last Answer : b) Once in 5 years *

Description : Periodical inspection of Welded girders a) Once in 3 years b) Once in 3 years* c) Once in 2 years d) Once in 5 years

Last Answer : b) Once in 3 years*

Description : Initial inspection for PSC girders / Welded girder bridges as per IRBM 1998 a) Within one year of installation* b) Once in 3 years d) Once in 2 years d) Once in 5 years

Last Answer : a) Within one year of installation*

Description : DFWR weld shall be replaced. (i) Within 2 months of detection. (ii) Within 1 year of detection. (iii) Within 3 months of detection.* (iv) after 3 days of detection.

Last Answer : (iii) Within 3 months of detection.*

Description : What is the validity of Provisional competency certificate? (i) Valid for executing 50 joints or six months whichever is earlier. (ii) Valid for executing 100 joints or six months whichever is earlier.* (iii) Valid for executing 50 joints. (iv) Valid for six months

Last Answer : (ii) Valid for executing 100 joints or six months whichever is earlier.*

Description : Type of competency certificate issued after TW-1 course? (i) Competency for two years (ii) Provisional competency.* (iii) Competency for six months (iv) Competency to do welding independently

Last Answer : (ii) Provisional competency.*

Description : The Assistant Divisional Engineer should inspect the equipment at every manned level crossing on the subdivision once in a) 2 months b) 3 months c) 4 months d) 6 months*

Last Answer : d) 6 months

Description : In case of an offence punished with fine only, an offender who is sentenced to pay a  fine exceeding Rs. 100, the imprisonment in default of payment of fine shall not exceed (a) Two months (b) Three months (c) Four months (d) Six months

Last Answer : (d) Six months.

Description : In case of an offence punished with fine only, an offender who is sentenced to pay a  fine of not exceeding Rs. 100 but exceeding Rs. 50, the imprisonment in default of  payment of fine shall not exceed (a) Two months (b) Three months (c) Four months (d) Six months.

Last Answer : (c) Four months

Description : In case of an offence punished with fine only, an offender who is sentenced to pay a  fine of not exceeding Rs. 50, the imprisonment in default of payment of fine shall not  exceed (a) Two months (b) Three months (c) Four months (d) Six months.

Last Answer : (a) Two months

Description : USFD testing of new AT weld will be done by ? (i) JE/SSE sectional (ii) Incharge SSE (iii) USFD machine operator* (iv) None of the above

Last Answer : (iv) None of the above

Description : New AT weld should be entered in TMS by ? (i) Sectional JE/SSE* (ii) Incharge SSE (iii) Welder (iv) None of the above

Last Answer : (i) Sectional JE/SSE*

Description : Cross sectional area of catch water drain should not be more than a) 0 .75 square meter* b) 0. 90 square meter c) 0. 80 square meter d). 50 square meter

Last Answer : a) 0 .75 square meter*

Description : Testing of welds by a) Dye penetrant test b) Magnetic particle inspection c) Radiographic inspection d) All the above*

Last Answer : d) All the above

Description : For a major bridge, the URN would comprise of a) single digit b)eight digits* c) six digits d) four digits

Last Answer : b)eight digits*

Description : The capacity of automatic flushing cistern connected with three urinal shall be (a) 05 litrs. (b) 10 litrs. (c) 12.5 litrs.* (d) None of these

Last Answer : (c) 12.5 litrs.*

Description : Whoever holds out any threat of injury to any public servant, or to any person in  whom he believes that public servant to be interested shall be punished with  imprisonment of either description for a term which may ... fine or with both. a) Six month b) Three month c) One year d) Two year

Last Answer : a) Six month, One thousand

Description : Resistance to the taking of property by the lawful authority of a public servant shall  be punished with simple imprisonment may extend_____ , or with fine which may extend to  ____ or with both a) One month, five hundred b) Three months, five hundred c) Six month, one thousand d) None of these

Last Answer : c) Six month, one thousand

Description : Investigation for important bridges may be carried out in which stage a) Technical feasibility study (reconnaissance survey) b) Techno-economic feasibility study (preliminary engineering survey) c) Detailed survey and project report stage (final location survey) d) All the above *

Last Answer : d) All the above

Description : Market demand curve for a commodity is a (a) Horizontal summation of all the individual demand curve for that product (b) Summation of demand curve of competitive products (c) Demand curve of average demand and price of previous six months (d) Projected demand schedule for next three months

Last Answer : (a) Horizontal summation of all the individual demand curve for that product 

Description : Service life in terms of total GMT carried for 52 kg. 90 UTS rail is:- (a) 425 GMT (b) 475 GMT (c) 525 GMT* (d) 545 GMT

Last Answer : (c) 525 GMT*

Description : The pressure on soil worked out shall be ……… the SBC of the soil. a) more than b) equal to c) not equal to d) less than*

Last Answer : d) less than*

Description : An accident has taken place at out station and main line is blocked and relief train is to be turned out without medical car. The hooter shall be: a. 3 long b. 4 long* c. 4 long, 1 short d. 3 long, and 1 short

Last Answer : b. 4 long

Description : The wash hand basin shall be fixed at a height of (a) 75-80 cm* (b) 75 cm (c) 80 cm (d) Not specified

Last Answer : (a) 75-80 cm*

Description : The capacity of automatic flushing cistern connected with two urinal shall be (a) 10 litrs.* (b) 12.5 litrs. (c) 05 litrs. (d) None of these

Last Answer : (a) 10 litrs.*

Description : The capacity of automatic flushing cistern connected with one urinal shall be (a) 05 litrs. (b) 10 litrs. (c) 12.5 litrs. (d) None of these

Last Answer : (a) 05 litrs.

Description : The urinal basin shall be connected with (a) High level floating cistern* (b) Low level floating cistern (c) Automatic floating cistern (d) Any one of the above

Last Answer : (a) High level floating cistern*

Description : For high level flush the nominal dia of flush pipe shall be (a) 32 mm* (b) 40 mm (c) 25 mm (d) None of these

Last Answer : a) 32 mm*

Description : Indian type W.C. pan shall have 10cm. S.C.I. trap P or S type with effective seal of (a) 5 cm.* (b) 10 cm. (c) 7.5 cm (d) None of these

Last Answer : (a) 5 cm.*

Description : The increased gain of 10 dbs for single line & ‘D’ marks rails on double/multiple lines shall be employed for classification of defects. (i) defect in weld (ii) defects in rail. * (iii) for both defects on weld & rail. (iv) None of above.

Last Answer : ii) defects in rail. *

Description : Rails used for A T Welding shall not normally be welded? (i) 20 years old . (ii) 30 years old (iii) 40 years old (iv) 50 years old*

Last Answer : iv) 50 years old*

Description : What is the speed restriction to be observed for train passing? (i) Necessary speed restriction shall be observed until the grinding operation is over.* (ii) 30KMPH (iii) 45 KMPH (iv) Not required

Last Answer : (i) Necessary speed restriction shall be observed until the grinding operation is over.*

Description : Pressure of Oxygen during pre-heating shall be? (i) 4.0 – 5.0 kg/ sq cm (ii) 5.0 – 6.0 kg/ sq cm (iii) 6.0 – 7.0 kg/ sq cm (iv) 7.0 – 8.0 kg/ sq cm *

Last Answer : (iv) 7.0 – 8.0 kg/ sq cm *

Description : ressure of LPG during pre-heating shall be? (i) 2.0 - 2.5 kg/ sq cm (ii) 2.0 - 2.5 kg/ sq cm (iii) 2.0 - 2.5 kg/ sq cm* (iv) 2.0 - 2.5 kg/ sq cm

Last Answer : (iii) 2.0 - 2.5 kg/ sq cm*

Description : Finished tolerance on 10 cm. long st. edge on surface of head shall be? (i) 0 to 0.1 mm (ii) 0 to 0.2 mm (iii) 0 to 0.4 mm* (iv) 0 to 0.3 mm

Last Answer : (iii) 0 to 0.4 mm*

Description : Finished tolerance on 10 cm long st. edge at the centre on gauge side shall be? (i) ± 0.4 mm (ii) ± 0.1 mm (iii) ± 0.2 mm (iv) ± 0.3 mm*

Last Answer : iv) ± 0.3 mm*

Description : Finished tolerance on 1 Mt. long st. edge on surface of head shall be? (i) 0 to .1 mm (ii) 1 to 1.5 mm (iii) 0 mm (iv) 0 to 1 mm*

Last Answer : (iv) 0 to 1 mm*

Description : Finished tolerance on 1 Mt. st. edge at the centre on gauge side shall be? (i) ± 0.2 mm (ii) ± 0.3 mm (iii) ± 0.5 mm* (iv) ± 1.0 mm

Last Answer : (iii) ± 0.5 mm*

Description : What is the validity after supervisors course (TW-3)? (i) Normally, supervisors shall not be required to undergo the course again. However, they may be sent for course on performance basis.* (ii) 2 years (iii) 5 Years (iv) 10 Years