Completion of an activity on CPM network diagram, is generally known
(A) Event
(B) Node
(C) Connector
(D) All the above

1 Answer

Answer :

(D) All the above

Related questions

Description : ................... is an event oriented network diagram. a. CPM b. PERT c. Histogram d. Ogive

Last Answer : b. PERT

Description : What is the benefit of using PERT/CPM network as integral component of project management? a. They furnish a consistent framework for planning, scheduling, monitoring and controlling project b. They illustrate ... that the project will be completed by a specific date d. All of the above

Last Answer : d. All of the above

Description : ......................... is activity oriented network diagram. a. CPM b. PERT c. Histogram d. Ogive

Last Answer : a. CPM

Description : The particular task performance in CPM is known  A.Dummy  B.Event  C.Activity  D.Contract.

Last Answer : C.Activity

Description : In a PERT network, slack time is _____. (a) The end point that represents the completion of a major activity (b) The time or resources required to progress from one event to another ( ... without delaying the whole Project (d) The longest or most time-consuming sequence of events and activities 

Last Answer : (c) The amount of time an individual activity can be delayed without delaying the whole Project 

Description : Select the correct statement. (A) Activity arrows in a CPM network are drawn to scale (B) The tail of an arrow represents the finish of an activity (C) Arrow bead represents the start of an activity (D) None of the above

Last Answer : (D) None of the above

Description : In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having (A) Longest duration (B) Highest cost slope (C) Least cost slope (D) Shortest duration

Last Answer : (C) Least cost slope

Description : _____________ refers to some action which is a time consuming effort necessary to complete a specific event. A. A Network. B. An Activity. C. An Event. D. A Node.

Last Answer : B. An Activity.

Description : In a network diagram, activity is denoted by ............................ a. Node b. Arrow c. Triangle d. None of these

Last Answer : b. Arrow

Description : Select the incorrect statement. (A) Earliest start of an activity is the early event time of the node it leaves. (B) Latest finish of an activity is the late event time of the node it enters. (C) Latest start of an activity is its latest finish minus its duration. (D) None of the above

Last Answer : (D) None of the above

Description : Pick up the incorrect statement from the following: (A) The activity is the time consuming part of a project (B) The beginning and end of a job, are called events (C) The activity ... maximum time, is called a node (D) Logically and sequentially connected activities and events form a network

Last Answer : (C) The activity which consumes maximum time, is called a node

Description : The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as (A) Duration (B) Total float (C) Free float (D) Interfering float

Last Answer : (C) Free float

Description : ____________ is a graphical representation of the various activity and event relating to a project. A. Network analysis. B. Scheduling technique. C. Logical Model. D. Network Diagram

Last Answer : D. Network Diagram

Description : _____________ is an event-oriented approach . A. CPM. B. GERT. C. PERT. D. WASP.

Last Answer : 1

Description : For an activity in a CPM analysis, the early Finish time is 13 and the late Finish time  is 13. Duration of activity is 6. Which of the following statements is true?  A.The early start is 6 B. ... of the activity is 13  C.The slack of this activity is 13  D.The activity is on the critical path

Last Answer : D.The activity is on the critical path

Description : ______________ is an activity-oriented approach. A. CPM B. PERT C. GERT D. WASP

Last Answer : A. CPM

Description : In the given figure, the network of a project represents (A) Activity of an excavation of a footing (B) Activity of an excavation which starts at event No. 1 and ends at even No. 2 (C) Activity of excavation which takes 8 units of time (D) None of thes

Last Answer : (C) Activity of excavation which takes 8 units of time

Description : Pick up the incorrect statement from the following a. The activity which consumes maximum time, is called a node b. The activity is the time consuming part of a project c. The beginning ... of a job, are called events d. Logically and sequentially connected activities and events form a network

Last Answer : a. The activity which consumes maximum time, is called a node

Description : For completion of a project, the critical path of the network represents (A) Minimum time (B) Maximum time (C) Maximum cost (D) Minimum cost

Last Answer : (A) Minimum time

Description : (i) Mention the event that induces the completion of the meiotic division of the secondary oocyte. (ii) Trace the journey of the ovum from the ovary, its fertilisation and further development until the implantation of the embryo. -Biology

Last Answer : (i)Secondary oocyte completes meiosis-ll only when a sperm enters its cytoplasm. It forms a larger cell, the ootid and a small cell, the second polar body. (ii)The secondary oocyte is ... and inner cell mass.The trophoblast attacheds to endometrium (implantation) and blastocyst gets embedded in it.

Description : After the celebration of the successful milestone completion, a project manager  will often do which of the following? Select one: a. Continue to increase the intensity of the project to achieve the ... milestone. e. Stretch the goals of the project team, making them more tough and rigorous.

Last Answer : c. Allow the team to reflect on finding new ways of approaching the project work.

Description : CPM is (A) Synthesising in concepts (B) Is built of activities oriented programme (C) Is based on time estimate (D) All the above

Last Answer : (D) All the above

Description : The first method invented for planning projects, was (A) Bar chart method (B) Milestone chart (C) Critical path method (CPM) (D) Programme Evaluation and Review Technique (PERT)

Last Answer : (A) Bar chart method

Description : A CPM family includes (A) CPA (Critical Path Analysis) (B) CPP (Critical Path Plotted) (C) MCE (Minimum Cost Expenditure) (D) All the above

Last Answer : (D) All the above

Description : The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as (A) Event (B) Free float (C) Dummy (D) Constrain

Last Answer : (C) Dummy

Description : Is there any social network connector?

Last Answer : At the bottom of this page are two Blog Feed and Questions Feed. On many sites, they are called RSS feeds.

Description : What is the other name for LAN Card ? 1) NIC 2) Network Connector 3) MODEM 4) Internet Card

Last Answer : 1) NIC

Description : What is the other name for LAN Card ? 1 NIC 2 Network Connector 3 MODEM 4 Internet Card

Last Answer : 1 NIC

Description : Which of the following is not true regarding enzymes? (A) They catalyze only a particular type of reaction (B) They remain active even after separation from the source (C) They are destroyed ... They are irreversibly destroyed at high temperature (E) Their activity depends on the pH of the solution

Last Answer : Answer : C

Description : Independent float is the amount of time by which:  A. Start of the activity can be delayed without affecting the EST of subsequent  activity  B. reduces the float of subsequent ... without affecting EST  D. completion of an activity can be delayed beyond earliest possible finishing time

Last Answer : A. Start of the activity can be delayed without affecting the EST of subsequent  activity

Description : What is a project phase? A. A collection of logically related project activities that culminate in the completion  of one or more deliverables (Ans.)  B. A singular activity that completes a ... that has very similar parts D. A consistent period of time that is used throughout a project

Last Answer : A. A collection of logically related project activities that culminate in the completion  of one or more deliverables (Ans.)

Description : An activity whose start or end cannot be delay without affecting total project completion time is called ______ activity a. Dummy b. Non-critical c. Critical d. Important

Last Answer : c. Critical

Description : At the completion of the forward and backward passes, the slack for an activity is given by the a. Difference between early start and early finish b. Difference between early start and ... c. Difference between latest start and early finish d. Difference between latest start and latest finish

Last Answer : c. Difference between latest start and early finish

Description : ........................... is the latest time by which an activity can be finished without delaying the completion of the project. a. LST b. LFT c. EFT d. EST

Last Answer : b. LFT

Description : ..................... is the duration by which an activity can be delayed without delaying the completion of the project. a. Earliest Start Time b. Earliest Finish Time c. Latest Start Time d. Latest Finish Time

Last Answer : c. Latest Start Time

Description : Slack time refers to (A) An activity (B) An event (C) Both event and activity (D) None of the above

Last Answer : (B) An event

Description : Pick up the correct statement from the following: (A) The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float' (B) ... C) The difference between total float and free float, is called interfering float (D) All the above

Last Answer : (D) All the above

Description : Select the incorrect statement. (A) Start float and finish float are always equal. (B) Total float can be either start float or finish float. (C) Start float and finish float need not be equal. (D) Start float and finish float are the differences between activity times and not event times.

Last Answer : (C) Start float and finish float need not be equal.

Description : Pick up the incorrect statement from the following: (A) The various functions under each activity, are shown by one bar on Bar Charts (B) Bar chart establishes the interdependency of one event on another (C) Only approximate percentage of the completed work is reported (D) None of these

Last Answer : (B) Bar chart establishes the interdependency of one event on another

Description : Slack time is associated with (a) A real activity (b) An event (c) Both event and real activity (d) Dummy activity

Last Answer : (b) An event

Description : In the diagram shown below, if rotor X and rotor Z rotate in same direction and rotor Y rotates in opposite direction, then specify the type of node vibration. A. Three node vibration B. Two node vibration C. Single node vibration D. None of the above

Last Answer : B. Two node vibration

Description : In the diagram shown below, if rotor X and rotor Z rotate in same direction and rotor Y rotates in opposite direction, then specify the type of node vibration. A. Three node vibration B. Two node vibration C. Single node vibration D. None of the above

Last Answer : B. Two node vibration

Description : The user generally applies _________ to access mainframe or super computer? (A) node (B) terminal (C) desktop (D) None of the Above

Last Answer : (B) terminal

Description : Pick up the correct statement from the following: (A) The earth work of cutting in trenches or borrow pits in fairly uniform ground is measured with the help of average depths of the dead men (B) ... a nor b is feasible, are measured from the fillings after deduction of voids (D) All the above

Last Answer : (D) All the above

Description : If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is (A) 4 days (B) 6 days (C) 10 days (D) 16 day

Last Answer : (D) 16 days

Description : If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be (A) 2.3% and 84.1% (B) 97.7% and 84.1% (C) 97.7 % and 15.9% (D) 15.9% and 97.7%

Last Answer : (A) 2.3% and 84.1%

Description : Updating may result in (A) Change of critical path (B) Decrease of project completion time (C) Increase of project completion time (D) All of the above

Last Answer : (D) All of the above

Description : The probability distribution taken to represent the completion of time in PERT analysis is (a) Normal Distribution (b) Bet Distribution (c) Gamma Distribution (d) Gaussain Distribution

Last Answer : (a) Normal Distribution

Description : A bar chart is commonly used because (a) It is simple to draw and easy to understand (b) It indicates at a glance the overall progress of the project (c) It shows critical ... critical activities (d) It incorporates uncertainties for delay in estimation of time required for completion of activities.

Last Answer : (a) It is simple to draw and easy to understand