Free float is mainly used to
(A) Identify the activities which can be delayed without affecting the total float of preceding
activity
(B) Identify the activities, which can be delayed without affecting the total float of succeeding
activity
(C) Establish priorities
(D) Identify the activities which can be delayed without affecting the total float of either the
preceding or succeeding activities

1 Answer

Answer :

(B) Identify the activities, which can be delayed without affecting the total float of succeeding
activity

Related questions

Description : The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as (A) Total float (B) Free float (C) Interfering float (D) Independent float

Last Answer : (D) Independent float

Description : Pick up the correct statement from the following: (A) The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float' (B) ... C) The difference between total float and free float, is called interfering float (D) All the above

Last Answer : (D) All the above

Description : The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as (A) Duration (B) Total float (C) Free float (D) Interfering float

Last Answer : (C) Free float

Description : The independent float affects only (A) Preceding activities (B) Succeeding activities (C) The particular activity involved (D) None of the above

Last Answer : (C) The particular activity involved

Description : Independent float is the amount of time by which:  A. Start of the activity can be delayed without affecting the EST of subsequent  activity  B. reduces the float of subsequent ... without affecting EST  D. completion of an activity can be delayed beyond earliest possible finishing time

Last Answer : A. Start of the activity can be delayed without affecting the EST of subsequent  activity

Description : The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as (A) Event (B) Free float (C) Dummy (D) Constrain

Last Answer : (C) Dummy

Description : .......................... is the duration by which an activity can be delayed without delaying the project. a. Slack b. Total float c. Both a and b d. None of these

Last Answer : b. Total float

Description : Select the incorrect statement. (A) Start float and finish float are always equal. (B) Total float can be either start float or finish float. (C) Start float and finish float need not be equal. (D) Start float and finish float are the differences between activity times and not event times.

Last Answer : (C) Start float and finish float need not be equal.

Description : In a PERT network, slack time is _____. (a) The end point that represents the completion of a major activity (b) The time or resources required to progress from one event to another ( ... without delaying the whole Project (d) The longest or most time-consuming sequence of events and activities 

Last Answer : (c) The amount of time an individual activity can be delayed without delaying the whole Project 

Description : The following statements relate to CPE credit units. Which is incorrect? a. One credit hour of CPE program, activity or source shall be equivalent to one (1) credit unit. b. Any excess ... carried over to the next three-year period including credit units earned for doctoral and master's degrees.

Last Answer : Excess credit units earned may be carried over to the next three-year period including credit units earned for doctoral and master's degrees.

Description : Whenever an activity has zero total float, then (A) Free float of the activity must be zero but independent float need not be zero (B) Independent float must be zero but free float need not be ... and independent float both must be zero (D) Free float and independent float both need not be zero

Last Answer : (C) Free float and independent float both must be zero

Description : Additional time which a non-critical activity can consume without increasing the project duration is called _____________. A. Total Float. B. Free Float C. Independent Float. D. Dependant Float

Last Answer : A. Total Float.

Description : Critical path moves along the activities having total float as (a) Positive (b) Negative ( c) Zero (d) Unity

Last Answer : ( c) Zero

Description : Activities which can be accomplished simultaneously are termed as ___________. A. Preceeding Activities. B. Succeeding Activities. C. Concurrent Activities D. Dummy Activities.

Last Answer : C. Concurrent Activities

Description : Activities which must be finished before a given event can occur are termed as _________. A. Preceeding Activities. B. Succeeding Activities C. Concurrent Activities D. Dummy Activities.

Last Answer : A. Preceeding Activities.

Description : Pick up the incorrect statement from the following: (A) The difference between the earliest start time and latest finish time of any activity, is the maximum time available for the activity (B) The ... start time and earliest start time of an activity, is called total float (D) None of thes

Last Answer : (D) None of these

Description : Total float for any activity is defined as the difference between (A) Its latest finish time and earliest start time for its successor activity (B) Its latest start time and earliest start ... earliest finish time (D) Its earliest finish time and earliest start time for its successor activity

Last Answer : (B) Its latest start time and earliest start time

Description : Mr. (A) is a manager in a manufacturing company, he attempts to establish a culture of quality affecting the attitudes and actions of every employee and relies on a workforce that wants to ... Management ; (b) Knowledge management ; (c) Operations Management (d) Management of Information System

Last Answer : (c) Operations Management

Description : A critical path network diagram does NOT: A. Help determine the amount of float B. Identify the particularly important activities C. Calculate earned value D. Calculate the duration of the whole project

Last Answer : C. Calculate earned value

Description : Which of the following is true about management meetings? Select one: a. They are short meetings to develop a common understanding of what the short-term  priorities are for the project. ... , tracking progress of existing plans, and  making adjustments to plans in response to new information.

Last Answer : e. They are oriented toward developing plans, tracking progress of existing plans, and  making adjustments to plans in response to new information.

Description :  Once the logic of a network is laid out, the project manager will conduct a forward  pass and a backward pass through the network. This will provide information regarding  ______ and will identify ... C. Resource shortages, high risk activities D. The high risk activities, non-critical path

Last Answer : A. The total duration of the project, critical path

Description : An activity whose start or end cannot be delay without affecting total project completion time is called ______ activity a. Dummy b. Non-critical c. Critical d. Important

Last Answer : c. Critical

Description : Mark the correct option. a) The first loan on PPF accounts can be taken in the third year from the year of opening the account. b) The amount of Loan will be restricted to 25% of the balance at ... is repayable either in lump sum or in convenient installments of not more than 36. d) All the above

Last Answer : d) All the above

Description :  In a project schedule, the sequence of activities which cannot be delayed during the  course of the project without extending the project end date is referred to as the:  A. Action plan B. Critical path C. Schedule baseline D. Slack line

Last Answer : B. Critical path

Description : ..................... is the duration by which an activity can be delayed without delaying the completion of the project. a. Earliest Start Time b. Earliest Finish Time c. Latest Start Time d. Latest Finish Time

Last Answer : c. Latest Start Time

Description : Pick up the correct statement from the following: (A) The tides at any place occur a little less than 1 hour later, each succeeding day (B) The influence of the earth's gravity alone produces level-tidal ... ) The spinning force is maximum at the equator and zero at the poles (D) All of the above

Last Answer : (D) All of the above

Description : Consider the following statements: In the critical path method of construction planning, Free Float can be. 1. Greater than Total Float. 2. Greater than Independent Float 3. Equal to Total Float. 4. Less than ... (B) 2 and 3 are correct (C) 1 and 4 are correct (D) 1 and 2 are correct

Last Answer : (B) 2 and 3 are correct

Description : Interfering float is the difference between (A) Total float and free float (B) Total float and independent float (C) Free float and independent float (D) None of the above

Last Answer : (A) Total float and free float

Description : The technique for establishing and maintaining priorities among the various jobs of a project, is known (A) Event flow scheduling technique (B) Critical ratio scheduling (C) Slotting technique for scheduling (D) Short interval scheduling

Last Answer : (B) Critical ratio scheduling

Description : Free float for any activity is defined as the difference between A. its earliest finish time and earliest start time for its successor activity B. its latest start time and earliest start time ... its successor activity D. its earliest finish time and latest start time for its successor activity

Last Answer : A. its earliest finish time and earliest start time for its successor activity

Description : Once the project is approved and moves into the planning stage, what happens  in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis

Last Answer : d. Risks are identified with each major group of activities.

Description : Once the project is approved and moves into the planning stage, what  happens in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis

Last Answer : d. Risks are identified with each major group of activities.

Description : A transit is oriented by setting its vernier A to read the back azimuth of the preceding line. A back sight on the preceding transit station taken and transit is rotated about its vertical axis. The vernier ... (C) Back bearing of the forward line (D) Equal to 360°-azimuth of the forward line

Last Answer : (A) Azimuth of the forward line

Description : The angle between the prolongation of the preceding line and the forward line of a traverse is called (A) Deflection angle (B) Included angle (C) Direct angle (D) None of the above

Last Answer : (A) Deflection angle

Description : Which one from the following is highly associated activity of project planning? (A) Keep track of the project progress. (B) Compare actual and planned progress and costs (C) Identify the activities, milestones and deliverables produced by a project (D) Both (B) and (C)

Last Answer : (C) Identify the activities, milestones and deliverables produced by a project

Description : In competitive enzyme activity inhibition (A) The structure of inhibitor generally resembles that of the substrate (B) Inhibitor decreases apparent Km (C) Km remains unaffective (E) Inhibitor decreases Vmax without affecting Km

Last Answer : Answer : A

Description : Consider the following statements: Identify the statement which implies natural justice. (A) The principle of natural justice is followed by the Courts. (B) Justice delayed is justice denied. (C ... right of a citizen (D) A reasonable opportunity of being heard must be given.

Last Answer : (D) A reasonable opportunity of being heard must be given.

Description : Total float in a planning network is (a) Late start time – Early start time (b) Early start time – Late start time (c) Late start time – Late finish time (d) Late finish time – Early finish time

Last Answer : Ans: (a & d)

Description : With Republicans succeeding in making abortion impossible in many red states, will we see a spike in crime in 15 years or so?

Last Answer : With the rise of the internet and so much entertainment I don’t believe so. However, I think they’ll still have their “Honorable, Patriotic” crop of people to have when it comes to military recruiting.

Description : Following and Succeeding at the Perfect Body Diet?

Last Answer : The perfect body diet is a newer one that is aimed towards helping the dieter achieve that perfect body through diet and exercise. There are a few tips for somebody who plans to follow this diet ... loose skin Following these simple tips will help you reach the perfect body you've always dreamed of.

Description : A cropping system where the land is hands over the succeeding crop before the harvest of standing crop.

Last Answer : Ans.Relay or overlapping cropping

Description : The seed of succeeding crops is sown broadcast at 10 to 15 days before harvesting rice crop?

Last Answer : Ans.Paira/Utera Crops

Description : Allelo-chemicals interfere with survival and growth of a).Neighbouring plants b). succeeding plants c). The donor plants themselves d). All

Last Answer : d). All

Description : PERT technique of network analysis is mainly useful for (A) Small projects (B) Large and complex projects (C) Research and development projects (D) Deterministic activities

Last Answer : (C) Research and development projects

Description : In case of a Rotameter, the density of the float material is __________ that of the liquid it replaces. (A) More than (B) Less than (C) Equal to (D) Either (A) or (B)

Last Answer : (A) More than

Description : The project schedule is used to determine all of the following except which one?  A. Cost estimates B. Activity start dates C. Float times D. Activity end dates

Last Answer : A. Cost estimates

Description : Which one of the following statements best defines procurement? a. A technique to establish the best approach for obtaining the resources for the project. b. A group of interrelated resources and ... product. d. The process by which products and services required for the project are acquired.

Last Answer : d. The process by which products and services required for the project are acquired.

Description : Which one of the following statements best defines procurement?  a. A technique to establish the best approach for obtaining the resources for the project.  b. A group of interrelated resources and ... product.  d. The process by which products and services required for the project are acquired.

Last Answer : d. The process by which products and services required for the project are acquired.

Description : Which one of the following activities will NOT help improve the ethical behaviour of a marketing firm? A)Help employees become aware of and sensitive toward ethical issues B)Redesign the company's culture ... tactics D)Establish and enforce a code of ethics E)Eliminate "bad apples" in the firm

Last Answer : C)Reward employees who use questionable business tactics

Description : To facilitate communication, marketing managers should A)emphasise the firm's marketing objectives. B)establish an information system within the marketing unit. C)form an open-communication group within the marketing unit. D)integrate marketing activities with other departments.

Last Answer : B)establish an information system within the marketing unit.