The independent float affects only
(A) Preceding activities
(B) Succeeding activities
(C) The particular activity involved
(D) None of the above

1 Answer

Answer :

(C) The particular activity involved

Related questions

Description : The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as (A) Total float (B) Free float (C) Interfering float (D) Independent float

Last Answer : (D) Independent float

Description : Free float is mainly used to (A) Identify the activities which can be delayed without affecting the total float of preceding activity (B) Identify the activities, which can be delayed ... which can be delayed without affecting the total float of either the preceding or succeeding activities

Last Answer : (B) Identify the activities, which can be delayed without affecting the total float of succeeding activity

Description : Pick up the correct statement from the following: (A) The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float' (B) ... C) The difference between total float and free float, is called interfering float (D) All the above

Last Answer : (D) All the above

Description : The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as (A) Duration (B) Total float (C) Free float (D) Interfering float

Last Answer : (C) Free float

Description : The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as (A) Event (B) Free float (C) Dummy (D) Constrain

Last Answer : (C) Dummy

Description : Independent float is the amount of time by which:  A. Start of the activity can be delayed without affecting the EST of subsequent  activity  B. reduces the float of subsequent ... without affecting EST  D. completion of an activity can be delayed beyond earliest possible finishing time

Last Answer : A. Start of the activity can be delayed without affecting the EST of subsequent  activity

Description : Whenever an activity has zero total float, then (A) Free float of the activity must be zero but independent float need not be zero (B) Independent float must be zero but free float need not be ... and independent float both must be zero (D) Free float and independent float both need not be zero

Last Answer : (C) Free float and independent float both must be zero

Description : Activities which can be accomplished simultaneously are termed as ___________. A. Preceeding Activities. B. Succeeding Activities. C. Concurrent Activities D. Dummy Activities.

Last Answer : C. Concurrent Activities

Description : Activities which must be finished before a given event can occur are termed as _________. A. Preceeding Activities. B. Succeeding Activities C. Concurrent Activities D. Dummy Activities.

Last Answer : A. Preceeding Activities.

Description : Additional time which a non-critical activity can consume without increasing the project duration is called _____________. A. Total Float. B. Free Float C. Independent Float. D. Dependant Float

Last Answer : A. Total Float.

Description : The following statements relate to CPE credit units. Which is incorrect? a. One credit hour of CPE program, activity or source shall be equivalent to one (1) credit unit. b. Any excess ... carried over to the next three-year period including credit units earned for doctoral and master's degrees.

Last Answer : Excess credit units earned may be carried over to the next three-year period including credit units earned for doctoral and master's degrees.

Description : For all positive reaction orders for a particular duty, (A) Mixed reactor is always larger than the plug-flow reactor (B) Ratio of the volume of the mixed reactor to that of the plug-flow ... (C) Reactor size is independent of the type of flow (D) Density variation during reaction affects design

Last Answer : (A) Mixed reactor is always larger than the plug-flow reactor

Description : Consider the following statements: In the critical path method of construction planning, Free Float can be. 1. Greater than Total Float. 2. Greater than Independent Float 3. Equal to Total Float. 4. Less than ... (B) 2 and 3 are correct (C) 1 and 4 are correct (D) 1 and 2 are correct

Last Answer : (B) 2 and 3 are correct

Description : Interfering float is the difference between (A) Total float and free float (B) Total float and independent float (C) Free float and independent float (D) None of the above

Last Answer : (A) Total float and free float

Description : Critical path moves along the activities having total float as (a) Positive (b) Negative ( c) Zero (d) Unity

Last Answer : ( c) Zero

Description : Choose the correct option according to given below  statement. Statement 1: Umbrella activities are independent of any one framework activity and occur throughout the process. Statement 2: quality assurance, ... . c. Only statement 3 is correct. d. Statement 1 and statement 3 are correct

Last Answer : b. Statement 1 and statement 2 are correct.

Description : Pick up the correct statement from the following: (A) The tides at any place occur a little less than 1 hour later, each succeeding day (B) The influence of the earth's gravity alone produces level-tidal ... ) The spinning force is maximum at the equator and zero at the poles (D) All of the above

Last Answer : (D) All of the above

Description : Pick up the incorrect statement from the following: (A) The difference between the earliest start time and latest finish time of any activity, is the maximum time available for the activity (B) The ... start time and earliest start time of an activity, is called total float (D) None of thes

Last Answer : (D) None of these

Description : Total float for any activity is defined as the difference between (A) Its latest finish time and earliest start time for its successor activity (B) Its latest start time and earliest start ... earliest finish time (D) Its earliest finish time and earliest start time for its successor activity

Last Answer : (B) Its latest start time and earliest start time

Description : Select the incorrect statement. (A) Start float and finish float are always equal. (B) Total float can be either start float or finish float. (C) Start float and finish float need not be equal. (D) Start float and finish float are the differences between activity times and not event times.

Last Answer : (C) Start float and finish float need not be equal.

Description : A transit is oriented by setting its vernier A to read the back azimuth of the preceding line. A back sight on the preceding transit station taken and transit is rotated about its vertical axis. The vernier ... (C) Back bearing of the forward line (D) Equal to 360°-azimuth of the forward line

Last Answer : (A) Azimuth of the forward line

Description : The angle between the prolongation of the preceding line and the forward line of a traverse is called (A) Deflection angle (B) Included angle (C) Direct angle (D) None of the above

Last Answer : (A) Deflection angle

Description : The range of a particular Rotameter can be increased by (A) Use of floats of different densities (B) No means (C) Increasing the diameter of the float (D) Decreasing the diameter of the float

Last Answer : (A) Use of floats of different densities

Description : The marketing concept is a way of thinking or a management philosophy that affects _____ 1. Only marketing activities 2. Most efforts of the organization 3. Mainly the efforts of sales personnel 4. Mainly customer relations 5. Only business organizations

Last Answer : Most efforts of the organization

Description : The marketing concept is a way of thinking or a management philosophy that affects: A)only marketing activities B)most efforts of the organisation C)mainly the efforts of sales personnel VU Cafeteria D)mainly customer relations E)only business organisations

Last Answer : B)most efforts of the organisation

Description : A critical path network diagram does NOT: A. Help determine the amount of float B. Identify the particularly important activities C. Calculate earned value D. Calculate the duration of the whole project

Last Answer : C. Calculate earned value

Description : With Republicans succeeding in making abortion impossible in many red states, will we see a spike in crime in 15 years or so?

Last Answer : With the rise of the internet and so much entertainment I don’t believe so. However, I think they’ll still have their “Honorable, Patriotic” crop of people to have when it comes to military recruiting.

Description : Following and Succeeding at the Perfect Body Diet?

Last Answer : The perfect body diet is a newer one that is aimed towards helping the dieter achieve that perfect body through diet and exercise. There are a few tips for somebody who plans to follow this diet ... loose skin Following these simple tips will help you reach the perfect body you've always dreamed of.

Description : A cropping system where the land is hands over the succeeding crop before the harvest of standing crop.

Last Answer : Ans.Relay or overlapping cropping

Description : The seed of succeeding crops is sown broadcast at 10 to 15 days before harvesting rice crop?

Last Answer : Ans.Paira/Utera Crops

Description : Allelo-chemicals interfere with survival and growth of a).Neighbouring plants b). succeeding plants c). The donor plants themselves d). All

Last Answer : d). All

Description : Free float for any activity is defined as the difference between A. its earliest finish time and earliest start time for its successor activity B. its latest start time and earliest start time ... its successor activity D. its earliest finish time and latest start time for its successor activity

Last Answer : A. its earliest finish time and earliest start time for its successor activity

Description : The project schedule is used to determine all of the following except which one?  A. Cost estimates B. Activity start dates C. Float times D. Activity end dates

Last Answer : A. Cost estimates

Description : .......................... is the duration by which an activity can be delayed without delaying the project. a. Slack b. Total float c. Both a and b d. None of these

Last Answer : b. Total float

Description : For providing a raft foundation, the following activities are involved 1. Ramming the foundation bed 2. Excavation of the soil upto required depth 3. Laying the reinforcement over the foundation bed 4. Curing the cement concrete placed over ... 2, 1 (C) 2, 1, 3, 5, 4 (D) 3, 2, 5, 1, 4

Last Answer : Answer: Option C

Description : When two events are independent the probability that one event occurs in no way affects the probability of the other event occurring true or false?

Last Answer : It is true.

Description : While scheduling a project by C.P.M. (A) A project is divided into various activities (B) Required time for each activity is established (C) Net work is drawn by connecting the activities and the events (D) All the above

Last Answer : (D) All the above

Description : Pick up the incorrect statement from the following: (A) The activity is the time consuming part of a project (B) The beginning and end of a job, are called events (C) The activity ... maximum time, is called a node (D) Logically and sequentially connected activities and events form a network

Last Answer : (C) The activity which consumes maximum time, is called a node

Description : In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having (A) Longest duration (B) Highest cost slope (C) Least cost slope (D) Shortest duration

Last Answer : (C) Least cost slope

Description : Is the electrical buzz that is preceding the thermostat/cooling system kicking in a sign that a component is about to die or that I'm at risk of an electical fire?

Last Answer : answer:Where exactly is the noise coming from? The thermostat or the cooler? - If the thermostat, try removing the faceplate. Does it have one of those mercury switches (little glob of mercury in a glass tube) ... the system to run without that fan. You'll probably want to get a pro to check it out.

Description : The following sentence is false. The preceding sentence is true. Are these sentences true or false? -Riddles

Last Answer : Neither, it's a paradox. If the first is true, then the second must be false, which makes the first false? it doesn't work.

Description : The following sentence is false. The preceding sentence is true. Are these sentences true or false? -Riddles

Last Answer : Neither, it's a paradox. If the first is true, then the second must be false, which makes the first false; it doesn't work.

Description : What is the coefficient of a term in a row of Pscal triangle if in the preceding row, the coeficient on the immediate left is 5 on the immediate rigth

Last Answer : What is the coefficient of a term in a row of Pscal triangle if in the preceding row, the ... immediate left is 5 on the immediate rigth is 10

Description : Pre-Harappan Cultures, Cultures of the period preceding the Harappan civilisation,

Last Answer : Find the incorrect pair from set B and write the correct ones: Set A' Set B' (a) ... The period after the decline of the mature (Urban) phase

Description : Relative to the direction of rotation, a D.C. motor commutating pole has the same polarity as the _____________. A. main pole following B. interpole following C. main pole preceding D. interpole preceding

Last Answer : Answer: C

Description : The transmitter technique adopted to reduce the noise effect of the preceding question is called A. noise masking B. anitnoise C. noise killing D. preemphasis

Last Answer : D. preemphasis

Description : In homologous series one member differs from the preceding member by

Last Answer : CH 2 group.

Description : The BACKTRACKING-SEARCH algorithm in Figure 5.3 has a very simple policy for what to do when a branch of the search fails: back up to the preceding variable and try a different value for it. This is ... also possible to go all the way to set of variable that caused failure. a) True b) False

Last Answer : a) True

Description : Mark the correct option. a) The first loan on PPF accounts can be taken in the third year from the year of opening the account. b) The amount of Loan will be restricted to 25% of the balance at ... is repayable either in lump sum or in convenient installments of not more than 36. d) All the above