1 Answer

Answer :

PERT - Progamme Evaluation and Review Techique.

Related questions

Description : What is the full form of 'PERT' ? -How To ?

Last Answer : The full form of 'PERT' is Project Evaluation and Review Technique

Description : If $190 is invested at an interest rate of 11% per year and is compounded continuously, how much will the investment be worth in 4 years Use the continuous compound interest formula: A = Pert?

Last Answer : 10001/999900

Description : Which one of the following is the most appropriate management control technique for timely completion of a project ? (A) Organisation chart (B) Management by Objectives (C) PERT (D) Span of control

Last Answer : Answer: PERT

Description : Why PERT is preferred over CPM for evaluation of project ?

Last Answer : PERT is based on the approach of multiple time estimates for each activity.

Description : Which of the following establishes key dates throughout the life of a project that  must be met for the project to finish on time? Select one: a. Critical path b. Ballpark estimate c. Pert diagram d. Slack chart e. Milestone schedule

Last Answer : e. Milestone schedule

Description : While assessing your project processes, you have identified some  uncontrolled process variations. Which of the following would be the  appropriate chart you may use for this purpose? Select one: a. Pareto diagram b. PERT chart c. Control chart d. HR personnel chart e. Critical path

Last Answer : c. Control chart

Description : In PERT (Project Evaluation and Review Technique) method Expected time (Te) is  A. (To+Tp+4Tm)/6  B. (To+Tp+2Tm)/6  C. (To+Tp+Tm)/6  D. (Tm+Tp+4To)/6

Last Answer : A. (To+Tp+4Tm)/6

Description : PERT (Project Evaluation and Review Technique) analysis is based on  A. Optimistic time, Pessimistic time and Most likely time  B.Pessimistic time, Optional time, Maximum time  C.Optimistic time, Efficient time, Most likely time  D.Minimax time, Optimistic time and harmonic time

Last Answer : A. Optimistic time, Pessimistic time and Most likely time

Description : PERT chart can be used to track the tasks of a project when task time estimates are  fairly uncertain.

Last Answer : Ans: True

Description : The statistical tool that depicts a project’s tasks and the relationships between those tasks is  known as (A) milestone (B) goal (C) Gantt chart (D) PERT chart

Last Answer : (D) PERT chart

Description : A horizontal bar chart that shows project tasks against a calendar is called (A) milestone (B) goal (C) Gantt chart (D) PERT chart

Last Answer : (C) Gantt chart

Description : . The PERT in project management means program evaluation and _____ technique. (A) resource (B) reconciliation (C) reconsideration (D) review

Last Answer : (D) review

Description : Which of the following statements is true? A. PERT is considered as a deterministic approach and CPM is a probabilis t ic techniques. B. PERT is considered as a probabilistic techniques ... and CPM are both probabilistic techniques. D. PERT and CPM are both considered as deterministic approachs

Last Answer : B. PERT is considered as a probabilistic techniques and CPM is considered as a deterministic approach

Description : dummy activity is used in PERT network to describe the (A) Precedence relationship (B) Resource idleness (C) Resource restriction (D) Necessary time delay

Last Answer : Option A

Description : In a PERT network, the earliest(activity) start time is the a. Earliest time that an activity can be finished without delaying the entire project b. Latest time that an activity can ... of precedence requirements d. Latest time that an activity can be finished without delaying the entire project

Last Answer : c. Earliest time that an activity can be started without violation of precedence requirements

Description : The basic difference between PERT and CPM is that a. PERT deals with events and CPM with activities b. Critical Path is determined in PERT only c. Costs are considered on CPM only d. Guessed times are used in PERT and evaluated times in CPM.

Last Answer : a. PERT deals with events and CPM with activities

Description : . In what year was PERT developed? a. 1957 b. 1959 c. 1960 d. 1958

Last Answer : . 1957

Description : What is the benefit of using PERT/CPM network as integral component of project management? a. They furnish a consistent framework for planning, scheduling, monitoring and controlling project b. They illustrate ... that the project will be completed by a specific date d. All of the above

Last Answer : d. All of the above

Description : For a project manager to have an effective means of identifying and communicating the planned activities and their interrelationships, he must use a network technique. One of the network ... evaluation review technique c. Path evaluation review technique d. Project execution review technique

Last Answer : b. Program evaluation review technique

Description : Consider the following features/factors: 1. Projects are of the non-repetitive type 2. Time required need not be known 3. Time required is known precisely 4. Events have been established for planning 5. Emphasis is given to ... and 4 (B) 3, 4 and 5 (C) 1, 3 and 4 (D) 1, 2 and 5

Last Answer : (A) 1, 2 and 4

Description : Which of the following is not a PERT event? (A) Site investigation started (B) Sessional work completed (C) Bus starts from Jaipur (D) Class is being attended

Last Answer : (D) Class is being attended

Description : The first method invented for planning projects, was (A) Bar chart method (B) Milestone chart (C) Critical path method (CPM) (D) Programme Evaluation and Review Technique (PERT)

Last Answer : (A) Bar chart method

Description : Pick up the PERT event from the following: (A) Digging of foundation started (B) Digging of foundation completed (C) Laying of concrete started (D) All the above

Last Answer : (D) All the above

Description : _________ technique helps to make a choice from numerous available alternatives a. PERT b. CPM c. Linear Programming d. Transportation

Last Answer : d. Transportation

Description : PERT is (A) An analytic in concept (B) Limited of event oriented diagrams (C) Used for research and development projects (D) All the above

Last Answer : (D) All the above

Description : PERT technique of network analysis is mainly useful for (A) Small projects (B) Large and complex projects (C) Research and development projects (D) Deterministic activities

Last Answer : (C) Research and development projects

Description : In PERT analysis, the time estimates of activities and probability of their occurrence follow (A) Normal distribution curve (B) Poisson's distribution curve (C) Beta distribution curve (D) None of the above

Last Answer : (C) Beta distribution curve

Description : The probability distribution taken to represent the completion of time in PERT analysis is (a) Normal Distribution (b) Bet Distribution (c) Gamma Distribution (d) Gaussain Distribution

Last Answer : (a) Normal Distribution

Description : A project activity has several components as indicated below; S.  No. Activity Preceded by Duration (in  Weeks) 1 A - 8 2 B A 6 3 C A 12 4 D B 4 5 E D 5 6 F B 12 7 G E& F ... H 5 10 J I & G 6 d. Prepare a PERT chart, estimate the duration of the project and identify the  critical path.

Last Answer : PERT Diagram based on Activity on Arrow  .  E  D 5 G B 5 9 J, 6 A 6 F,12 I ,5 8 c 12 H 8 OR  PERT Diagram based on Activity on Node …………………….6 marks a. Critical Path: A-B-F-G-J …………………….1 mark  b. Estimated Project Duration: 41 weeks

Description : For rotary cutting blade the proper cutting quality is affected by A)rates of forward speed to blade pert pheral speed B)radius of rotation of cutting blade C)feed per blade D)all of these

Last Answer : D)all of these

Description : PERT emphasises on ........................... a. Activity b. Time c. Cost d. None of these

Last Answer : b. Time

Description : ................... is an event oriented network diagram. a. CPM b. PERT c. Histogram d. Ogive

Last Answer : b. PERT

Description : ......................... is activity oriented network diagram. a. CPM b. PERT c. Histogram d. Ogive

Last Answer : a. CPM

Description : PERT stand for: a. Performance Evaluation Review Technique b. Programme Evaluation Review Technique c. Programme Evaluation Research Technique

Last Answer : b. Programme Evaluation Review Technique

Description : ______________ is an activity-oriented approach. A. CPM B. PERT C. GERT D. WASP

Last Answer : A. CPM

Description : _____________ is an event-oriented approach . A. CPM. B. GERT. C. PERT. D. WASP.

Last Answer : 1

Description : PERT stands for __________. A. Programme Evaluation and Research Techniques. B. Project Evaluation and Review Techniques. C. Programme Evaluation and Review Techniques. D. Project Evaluation and Research Techniques.

Last Answer : C. Programme Evaluation and Review Techniques.

Description : In a PERT network, slack time is _____. (a) The end point that represents the completion of a major activity (b) The time or resources required to progress from one event to another ( ... without delaying the whole Project (d) The longest or most time-consuming sequence of events and activities 

Last Answer : (c) The amount of time an individual activity can be delayed without delaying the whole Project