Description : What is the full form of 'PERT' ? -How To ?
Last Answer : The full form of 'PERT' is Project Evaluation and Review Technique
Description : If $190 is invested at an interest rate of 11% per year and is compounded continuously, how much will the investment be worth in 4 years Use the continuous compound interest formula: A = Pert?
Last Answer : 10001/999900
Description : Which one of the following is the most appropriate management control technique for timely completion of a project ? (A) Organisation chart (B) Management by Objectives (C) PERT (D) Span of control
Last Answer : Answer: PERT
Description : Why PERT is preferred over CPM for evaluation of project ?
Last Answer : PERT is based on the approach of multiple time estimates for each activity.
Description : Which of the following establishes key dates throughout the life of a project that must be met for the project to finish on time? Select one: a. Critical path b. Ballpark estimate c. Pert diagram d. Slack chart e. Milestone schedule
Last Answer : e. Milestone schedule
Description : While assessing your project processes, you have identified some uncontrolled process variations. Which of the following would be the appropriate chart you may use for this purpose? Select one: a. Pareto diagram b. PERT chart c. Control chart d. HR personnel chart e. Critical path
Last Answer : c. Control chart
Description : In PERT (Project Evaluation and Review Technique) method Expected time (Te) is A. (To+Tp+4Tm)/6 B. (To+Tp+2Tm)/6 C. (To+Tp+Tm)/6 D. (Tm+Tp+4To)/6
Last Answer : A. (To+Tp+4Tm)/6
Description : PERT (Project Evaluation and Review Technique) analysis is based on A. Optimistic time, Pessimistic time and Most likely time B.Pessimistic time, Optional time, Maximum time C.Optimistic time, Efficient time, Most likely time D.Minimax time, Optimistic time and harmonic time
Last Answer : A. Optimistic time, Pessimistic time and Most likely time
Description : PERT chart can be used to track the tasks of a project when task time estimates are fairly uncertain.
Last Answer : Ans: True
Description : The statistical tool that depicts a project’s tasks and the relationships between those tasks is known as (A) milestone (B) goal (C) Gantt chart (D) PERT chart
Last Answer : (D) PERT chart
Description : A horizontal bar chart that shows project tasks against a calendar is called (A) milestone (B) goal (C) Gantt chart (D) PERT chart
Last Answer : (C) Gantt chart
Description : . The PERT in project management means program evaluation and _____ technique. (A) resource (B) reconciliation (C) reconsideration (D) review
Last Answer : (D) review
Description : Which of the following statements is true? A. PERT is considered as a deterministic approach and CPM is a probabilis t ic techniques. B. PERT is considered as a probabilistic techniques ... and CPM are both probabilistic techniques. D. PERT and CPM are both considered as deterministic approachs
Last Answer : B. PERT is considered as a probabilistic techniques and CPM is considered as a deterministic approach
Description : dummy activity is used in PERT network to describe the (A) Precedence relationship (B) Resource idleness (C) Resource restriction (D) Necessary time delay
Last Answer : Option A
Description : In a PERT network, the earliest(activity) start time is the a. Earliest time that an activity can be finished without delaying the entire project b. Latest time that an activity can ... of precedence requirements d. Latest time that an activity can be finished without delaying the entire project
Last Answer : c. Earliest time that an activity can be started without violation of precedence requirements
Description : The basic difference between PERT and CPM is that a. PERT deals with events and CPM with activities b. Critical Path is determined in PERT only c. Costs are considered on CPM only d. Guessed times are used in PERT and evaluated times in CPM.
Last Answer : a. PERT deals with events and CPM with activities
Description : . In what year was PERT developed? a. 1957 b. 1959 c. 1960 d. 1958
Last Answer : . 1957
Description : What is the benefit of using PERT/CPM network as integral component of project management? a. They furnish a consistent framework for planning, scheduling, monitoring and controlling project b. They illustrate ... that the project will be completed by a specific date d. All of the above
Last Answer : d. All of the above
Description : For a project manager to have an effective means of identifying and communicating the planned activities and their interrelationships, he must use a network technique. One of the network ... evaluation review technique c. Path evaluation review technique d. Project execution review technique
Last Answer : b. Program evaluation review technique
Description : Consider the following features/factors: 1. Projects are of the non-repetitive type 2. Time required need not be known 3. Time required is known precisely 4. Events have been established for planning 5. Emphasis is given to ... and 4 (B) 3, 4 and 5 (C) 1, 3 and 4 (D) 1, 2 and 5
Last Answer : (A) 1, 2 and 4
Description : Which of the following is not a PERT event? (A) Site investigation started (B) Sessional work completed (C) Bus starts from Jaipur (D) Class is being attended
Last Answer : (D) Class is being attended
Description : The first method invented for planning projects, was (A) Bar chart method (B) Milestone chart (C) Critical path method (CPM) (D) Programme Evaluation and Review Technique (PERT)
Last Answer : (A) Bar chart method
Description : Pick up the PERT event from the following: (A) Digging of foundation started (B) Digging of foundation completed (C) Laying of concrete started (D) All the above
Last Answer : (D) All the above
Description : _________ technique helps to make a choice from numerous available alternatives a. PERT b. CPM c. Linear Programming d. Transportation
Last Answer : d. Transportation
Description : PERT is (A) An analytic in concept (B) Limited of event oriented diagrams (C) Used for research and development projects (D) All the above
Description : PERT technique of network analysis is mainly useful for (A) Small projects (B) Large and complex projects (C) Research and development projects (D) Deterministic activities
Last Answer : (C) Research and development projects
Description : In PERT analysis, the time estimates of activities and probability of their occurrence follow (A) Normal distribution curve (B) Poisson's distribution curve (C) Beta distribution curve (D) None of the above
Last Answer : (C) Beta distribution curve
Description : The probability distribution taken to represent the completion of time in PERT analysis is (a) Normal Distribution (b) Bet Distribution (c) Gamma Distribution (d) Gaussain Distribution
Last Answer : (a) Normal Distribution
Description : A project activity has several components as indicated below; S. No. Activity Preceded by Duration (in Weeks) 1 A - 8 2 B A 6 3 C A 12 4 D B 4 5 E D 5 6 F B 12 7 G E& F ... H 5 10 J I & G 6 d. Prepare a PERT chart, estimate the duration of the project and identify the critical path.
Last Answer : PERT Diagram based on Activity on Arrow . E D 5 G B 5 9 J, 6 A 6 F,12 I ,5 8 c 12 H 8 OR PERT Diagram based on Activity on Node …………………….6 marks a. Critical Path: A-B-F-G-J …………………….1 mark b. Estimated Project Duration: 41 weeks
Description : For rotary cutting blade the proper cutting quality is affected by A)rates of forward speed to blade pert pheral speed B)radius of rotation of cutting blade C)feed per blade D)all of these
Last Answer : D)all of these
Description : PERT emphasises on ........................... a. Activity b. Time c. Cost d. None of these
Last Answer : b. Time
Description : ................... is an event oriented network diagram. a. CPM b. PERT c. Histogram d. Ogive
Last Answer : b. PERT
Description : ......................... is activity oriented network diagram. a. CPM b. PERT c. Histogram d. Ogive
Last Answer : a. CPM
Description : PERT stand for: a. Performance Evaluation Review Technique b. Programme Evaluation Review Technique c. Programme Evaluation Research Technique
Last Answer : b. Programme Evaluation Review Technique
Description : ______________ is an activity-oriented approach. A. CPM B. PERT C. GERT D. WASP
Last Answer : A. CPM
Description : _____________ is an event-oriented approach . A. CPM. B. GERT. C. PERT. D. WASP.
Last Answer : 1
Description : PERT stands for __________. A. Programme Evaluation and Research Techniques. B. Project Evaluation and Review Techniques. C. Programme Evaluation and Review Techniques. D. Project Evaluation and Research Techniques.
Last Answer : C. Programme Evaluation and Review Techniques.
Description : In a PERT network, slack time is _____. (a) The end point that represents the completion of a major activity (b) The time or resources required to progress from one event to another ( ... without delaying the whole Project (d) The longest or most time-consuming sequence of events and activities
Last Answer : (c) The amount of time an individual activity can be delayed without delaying the whole Project